Completion Date2025
ClientNorthern Beaches Council
LocationWhale Beach, NSW
CategoryRemediation & Earthworks
SCOPE OF WORKS
Convil Group has undertaken reconstruction of 2m high, 12m long retaining wall to remediate the failed retaining wall along Whale Beach Rd.
The scope of works included:
- Site clearing and excavate to form a safe batter.
- Install Class 1 Timber Log Piles, including auguring up to 3m into sandstone rock and waterproofing.
- Install 120m of timbers as lagging for the retaining wall.
- Install sandstone logs.
- Reconstruct footpaths, kerb & gutter and fencing along the failed area.