Completion Date2022
ClientSutherland Shire Council
LocationBellingara NSW
CategoryRemediation & Earthworks / Landscaping & Public Spaces

SCOPE OF WORKS

This project involved the excavation and removal of 12 existing Netball courts for the construction of new courts.

The scope of works for this project includes:

  • Excavation and disposal of over 3000 m3 including asphalt, concrete and earth.
  • Construction of 40 m long sandstone block wall.
  • Construction of 50 m long masonry block retaining wall including concrete footing and drainage.
  • Supply and install 120 m of Chainwire fencing.
  • Construction of 7500 m2 of concrete 150 mm thick reinforced pavement.
  • Supply and install of over 350m of PVC drainage pipe ranging between 150mm to 600mm.
  • Construction of 15 new stormwater pits.
  • Construction of 550 m2 of asphaltic pavement.
  • Supply and install 200 m of trench grate.
  • Construction and coordination of 28 new sports lighting poles.
  • Reconstruction of 450 m2 of concrete footpath.
  • Reconstruction of 60 m of kerb and gutter.
  • Supply and application of 6500m2 of acrylic court surface paint.