SCOPE OF WORKS

  • Construction of concrete basketball court pavement with Plexi Pave acrylic hard-court paving.
  • Construction of footing and piers for the installation of Basketball hoops and futsal goal posts.
  • Construction of ramps with handrails, concrete footpath, footing, piers, edge beams and other slabs for fencing.
  • Installation of stormwater drainage including installation of pits, lintel and grates.
  • Installation of furniture, Basketball hoops and Futsal goalposts.
  • Construction of 600mm wide concrete dish drain.
  • Installation of 3m high black PVC Chainmesh fencing and with Chainmesh gate for along the perimeter of basketball court.
  • Blue and while line marking on the finished basketball court surface in accordance with FIBA guidelines.
  • Surrounding planting, landscaping and installation of street furniture.
Image shows Dawes park sports courts constructed by Convil Group