SCOPE OF WORKS

  • Excavation and compaction of several thousands of cubes of material for cut and fill operations.
  • Safe excavation and disposal of several thousand tonnes of asbestos-contaminated material, accompanied by the installation of thousands of square metres of orange Hi-Vis geotextile warning layer.
  • Placement and compaction of more than 6300 tonnes of structural fill and roadbase.
  • Installation of headwalls and riprap structures as per project specifications.
  • Implementation of biofiltration stormwater pits and Reinforced Concrete Pipe (RCP) installations.
  • Construction of various kerb and gutter configurations, including reinforcement dish drain, slotted kerb, barrier, and mountable kerbs.
  • Construction of multiple reinforced concrete raised threshold and footpath.
  • Establishment of biofiltration islands and blister islands to enhance environmental sustainability.
  • Application of several thousands of square metres of asphaltic concrete surfacing.
  • Reconstruction of pits, including grates and lintels.
  • Made provisions for the installation of electrical boom gates, including underboring.
  • Demolition of steel beams and concrete-reinforced footings and walls from a heritage coal hopper.
  • Constructed a hopper bridging structure to showcase the heritage hopper beneath the footpath, including the installation of steel rebar, waffle pods, concrete for a suspended slab, 360UB57 steel beams and angles, fake coloured coal, a glass walkable surface panel, and brass feature balustrades.
  • Installation of guardrail and terminals, and pedestrian fencing.
  • Construction of concrete block retaining walls with footings.
  • Laying of turf and several thousand trees and shrubs.
  • Installation of various signage and line marking.