Convil Group

Completion Date2023
ClientHawkesbury City Council
LocationGlossodia NSW
CategoryComplex Infrastructure / Remediation & Earthworks

SCOPE OF WORKS

  • Cut and fill of several thousand cubes.
  • Installation of a new stormwater system, involving:
    • Installation of approximately 500m of Fibre Reinforced Concrete Pipe (FRCP), ranging from 375mm to 600mm in diameter.
    • Construction of new kerb inlet pits with lintels and gully grates, including extended chamber pits to accommodate existing sewer services.
    • Construction of a single cell headwall with a rip rap discharge system and a turfed swale.
  • Profiling, regrading, and resheeting of 4400m2 of deep lift asphalt road pavement.
  • Construction of over 1000m of new kerb and gutter (SA) with subsoil drainage.
  • Repair of subgrade using stabilised roadbase for unsuitable materials.
  • Box out and subbase construction of approximately 2000m2 of road shoulder.
  • Construction of a concrete sleeper retaining wall.
  • Reconstruction and regrading of driveway crossovers to align with new layback levels, ensuring seamless transitions. Driveways include various materials such as plain and coloured concrete, pavers, asphalt, and roadbase.
  • Regrading and shaping of over 4000m2 of nature strip to match new kerb levels including the installation of over 4000m2 of various turfs.
  • Installation of signage and road markings to suit the newly constructed road.