Completion Date2024
ClientNorthern Beaches Council
LocationQueenscliff, NSW
CategoryComplex Infrastructure / Remediation & Earthworks
SCOPE OF WORKS
This project included the construction of a headland ramp and associated road and pedestrian upgrades. The scope of works includes:
- Major rock excavation and clearing of cliff face to accommodate footpaths and a FRP path structure.
- Removal of signage, road signs and trees.
- 250sqm Shotcrete along the cliff face including rock anchors and a mock sandstone finish to match existing landscape.
- Construction of a stainless-steel superstructure including piering into rock foundation and FRP installation.
- Construction of raised pedestrian crossing, footpaths, kerb & gutter, gutter bridge, and pram ramps.
- Adjustments to existing lid levels to match new levels.
- Construction of a sandstone block retaining.
- RMS Fencing installation, signage, linemarking, and landscaping.