Convil Group

Completion Date2024
ClientCanterbury Bankstown Council
LocationEarlwood, NSW
CategoryComplex Infrastructure

SCOPE OF WORKS

City of Canterbury-Bankstown had awarded Convil Group to complete road and pedestrian upgrades to Earlwood Town Centre. The project consisted of works at 9 locations within Earlwood’s HPAA. The scope of works includes:

    • Removal of 17 trees located outside shopfronts in a high-density area.
    • Excavation and removal of 350 sqm of pavers, footpaths, kerb ramps, islands, kerb & gutter including laybacks, dish drains and lintels & frames.
    • Stormwater upgrade involving installation of RCP, pits, extended chamber pits including lintels, and grates and frames to suit.
    • Realignment of kerb & gutter including adjustment to levels. Includes the adjustment of levels for the footpath and road levels to suit.
    • 650T of asphalting resheeting including intersections, carpark entries, road pavement and thresholds.
    • Construction of 11 raised asphalt speedhumps including apron resheeting.
    • Construction of 3 reinforced concrete thresholds.
    • Construction of a new concrete raised pedestrian crossing including kerb & gutter realignment and hardstand construction.
    • Reconstructing of 2 existing concrete raised pedestrian crossings.
    • Construction of concrete, paver pavements and permeable paving.
    • Installation of 21sqm of tactile indicators and 100 m of RMS Type 5 fencing, handrails, bollards, and street furniture.
    • Planting of 15 x 400L trees including tree pits and root barrier systems in an area with a significant number of services.
    • Landscaping, planting and turf installation.
    • Linemarking and signage associated with all raised thresholds and other road modifications.