Completion Date2025
ClientLiverpool City Council
LocationLiverpool NSW
CategoryStreetscapes & Cycleways / Complex Infrastructure
SCOPE OF WORKS
Liverpool City Council contracted Convil Group to undertake streetscape works at Macquarie St in Liverpool. The project provides a major revitalisation to Liverpool CBD.
These works consist of the following:
- Demolition and disposal of 4000sqm pavers and concrete subbase.
- Laying 4000sqm of granite pavers.
- Form, reinforce and pour 4000sqm reinforced concrete concrete pad with sand-cement mortar.
- Sealing and caulking 4000sqm of pavers and 600m of K&G.
- 3000sqm of hot mix asphalt resheeting including saw cutting, removal of loose debris, disposal, laying and compaction.
- Demolition of existing 200sqm concrete pedestrian crossing.
- Reconstruction of a 200sqm concrete pedestrian crossing with trafficable cobblestone pattern granite paver infills in a decorative pattern using Laticrete 3701 Admix and Laticrete 290 Adhesive including a 200mm reinforced concrete subbase.
- Demolition of more than 600m of concrete kerb & gutter, ramps, and laybacks.
- Construction of more than 720sqm of concrete subbase for kerb & gutter, ramps, and laybacks.
- Construction of more than 600m of granite bluestone kerb & gutter, ramps, and laybacks.
- Reconstruction and modification to 48 x stormwater drainage pits including the installation of 9 x bluestone lintels for EKI pits.
- Cutting, modifying and reconstructing 135m of existing stormwater pipe.
- Construction of 28 x tree pits including filtapaving, planting of some trees, stratavault systems and NDD.
- Installation of 73 x metal and timber seating.
- Installation of more than 120m of custom curved off-form concrete seating including LED undermounted lighting strips.
- Installation of 11 x 240L bins.
- Installation of a drinking fountain including a Sydney Water tap in and plumbing provisions.
- Installation of 18 x bike stands.
- Installation of 24 x bollards.
- Restoration of a 200sqm canopy structure spanning up to 10m high including installing 38 x new street grade downlights, 45m of LED strips and sealing/painting the entire structure.
- 48 x telstra pit reconstruction/adjustment including asbestos pits.
- Minor water and gas utility adjustments.
- Installation of 53 x new 600x600x800mm and 450x450x800mm GRC communication pits with paver infill covers.
- Installation of 279 x LED floor lighting including all provisions such as conduits, upturns and connections, backfill, installation of individual housing unit, installation of individual drainage for each lighting strip including a free draining sump, cutting of pavers to suit, caulking and temporary make safe while works is undertaken for each LED strip.
- Installation of 106 tree lights including all provisions such as conduits, upturns and connections, backfill, installation of individual housing unit, installation of individual drainage for each tree light including a free draining sump, core-drilling pavers to suit, caulking and temporary make safe while works is undertaken for each tree light.
- Installation of 21 x smart lighting poles including all provisions such as conduit works, footings including cantilevered ones, investigative works for services and connections.
- Provisions for the new Main Switch Board including pillar, connection from existing O/G pillar.
- More than 1850m of trenching completed for the electrical conduits most of which through NDD and approx. 10,000m of conduit laid within these trenches.
- Landscaping including turfing and planting of shrubs.
- Installation of fixtures, signage and line marking.
- Preservation of heritage features including culverts, artworks, pavers and mosaics.