Completion Date2023
ClientCity of Parramatta Council
LocationParramatta NSW
CategoryComplex Infrastructure
SCOPE OF WORKS
- Installation of new streetlights, complete with type 2 ragbolts and foundations.
- Installation of floodlights on streetlight columns.
- Constructed kerb and gutter, including kerb-only sections.
- Built reinforced concrete footpaths.
- Constructed two new raised threshold, incorporating oxides mixed into the concrete with a brick pattern stencil.
- Removed and constructed new on-grade pits of varying sizes, complete with lintels and Bike-Safe grates and frames.
- Converted kerb inlet pits into junction pits.
- Laid RRJ class 3 RCP stormwater pipes.
- Installation of asphaltic concrete as a deeplift.
- Installed signposting and new line markings.